An application running on a production cluster failed over to the backup node, however, the DLPARintegration scripts failed. On inspection, it was discovered that the scripts failed as a result of /var being 100% full. The administratoradded more space to /var and ran the following command: Which of the following is the correct next action?()

  • A、Refresh the RMC daemon using rmcctrl
  • B、Refresh the RSCT subsystem using SRC
  • C、Recover from script failure using clruncmd
  • D、Reconfigure the RSCT subsystem using recfgct
正确答案:A