A failure of the primary data center has occurred.  A warm site is available for use.  Which of the following should be done FIRST to bring the critical applications online?()

  • A、Run cabling and power to the warm site.
  • B、Restore data to the equipment.
  • C、Transfer all data tapes over to the warm site.
  • D、Restore least critical applications online to test to make sure the site is functioning.
正确答案:B