Based on which two conditions can master Preventive Maintenance (PM) schedules be created?()
- A、 elapsed time since the target start date or completion date of previous work generated by PM
- B、 difference between completion date of previous work and system date is equal to Lead Time
- C、 elapsed time since the target start date or completion date of the latest work orders for the asset
- D、 metered equipment usage since the target start date or completion date of previous work generated by PM
- E、 metered equipment usage since the target start date or completion date of the latest work order for the asset
正确答案:A,D