Based on which two conditions can master Preventive Maintenance (PM) schedules be created?()

  • A、 elapsed time since the target start date or completion date of previous work generated by PM  
  • B、 difference between completion date of previous work and system date is equal to Lead Time  
  • C、 elapsed time since the target start date or completion date of the latest work orders for the asset
  • D、 metered equipment usage since the target start date or completion date of previous work generated by PM
  • E、 metered equipment usage since the target start date or completion date of the latest work order for the asset
正确答案:A,D