Company.com has recently received a new p5-570 in the data center and intends to Micro-Partition the server. In which order should installation steps be taken?()
- A、Connect to the network,power on the server,Micro-Partition the server
- B、Connect to the HMC,power on the server,Micro-Partition the server,connect to the network
- C、Power on server,connect to the network,Micro-Partition the server,connect to the HMC
- D、Power on the server,connect to the HMC,Micro-Partition the server,connect to the network
正确答案:B