A new p5 customer has just installed a partitioned p5-550 alongside some older POWER4 servers.  The pSeries technical specialist has received a call to say that the existing HMC (7315) cannot connect to the new server.  How can the specialist help the customer?()

  • A、Explain to the customer that they need an additional HMC for the POWER5 system.
  • B、Obtain a PO from the customer to purchase additional serial connections to the HMC.
  • C、Obtain a PO from the customer to purchase additional Ethernet connections to the HMC.
  • D、Explain to the customer that they need a firmware update on the HMC to support both POWER4 and POWER5.
正确答案:A
答案解析:
进入题库查看解析