Conducting a project kick-off in the plan phase provides which of the following customer benefits? Select exactly 1 answer(s) from the following:()。

  • A、ensure that it receives detailed network diagrams
  • B、reduce the risk of downtime due to facilities-related problems
  • C、ensure end-user support immediately after the launch of a new system
  • D、confirm project roles and responsibilities, as well as milestone dates
正确答案:D