An AIX 5.3 customer has a Power 780 in a 2-meter (T42) rack. This rack needs to be moved six inches (15cm) to allow under-floor access. What preparation for moving the rack will result in the least disruption to end-users?()
- A、Initiate LPAR fallover to backup systems.
- B、Use Live Partition Mobility to move the LPARs to other systems.
- C、Use Live Application Mobility to move critical applications to alternate systems.
- D、Back up all LPARS to a NIM server and restore them to other LPARs on other systems.
正确答案:B
答案解析:有