The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()

  • A、Evaluate phase exit milestones using sufficiency criteria
  • B、Flexible entry and exit criteria to minimize schedule delays
  • C、Quality measures reported only to the project steering committee
  • D、Many work teams with few members to maximize the number of deliverable hand-offs
正确答案:A
答案解析:
进入题库查看解析