Which of the following is the FIRST course of action before implementing a change to a server?()
- A、 Survey users to get their response to the potential server change.
- B、 The change should be approved by management.
- C、 Switch over to the alternate site so users are not affected.
- D、 Implement RAID so the server does not go offline.
正确答案:B