Which two of the following activities are included in the Cisco Unified Communications project closeout()

  • A、Complete Ongoing Support Handoff Materials
  • B、Prepare for Handoff Meeting
  • C、Update Leading Practices
  • D、Obtain Customer Satisfaction Feedback
正确答案:C,D