During the process of fallover testing, a client/server database needs to be tested. On the AIX Server, start/stop/cleanup scripts and server application functionality have been tested. Before moving onto the next step of fallover testing,what action must be completed?()
- A、 Run who -a and validate that client connections are restored.
- B、 Verify that the client side application is functioning properly.
- C、 Check hacmp.out log file to validate that the application server started.
- D、 Verify that the application will successfully stop and restart on the fallover node.
正确答案:B
答案解析:有