As a rule of thumb for QA (Quality Assurance) activities, how many hours of downstream QA (Quality Assurance) costs are saved for each hour spent on technical reviews early in the project?()
- A、Up to 5
- B、Up to 10
- C、Up to 15
- D、Up to 20
正确答案:B