Which is the MOST effective method for generating support for your project plan?()

  • A、Requiring stakeholders to sign-off on project plan components
  • B、Requesting input from all stakeholders during the planning process
  • C、Providing an open line of communication regarding the project
  • D、Clearly illustrating how the project relates to the company’s objectives
正确答案:B