You have created a resource plan, DAY. You execute the following code: SQL> BEGIN DBMS_RESOURCE_MANAGER.CREATE_SIMPLE_DIRECTIVE ( PLAN => ’DAY’, COMMENT => ’DEPARTMENTS PLAN’, GROUP_OR_SUBPLAN => ’DEPARTMENTS’, CPU_P1=0); END; Then, you issue the following code: SQL> BEGIN DBMS_RESOURCE_MANAGER.CREATE_SIMPLE_DIRECTIVE ( PLAN => ’DAY’, COMMENT => ’DEPARTMENTS PLAN’, GROUP_OR_SUBPLAN => ’DEVELOPERS’, CPU_P2=100); END; What will be the impact of executing the above code?()
- A、 The DEVELOPERS and DEPARTMENTS subplans will be allocated CPU equally.
- B、 The DEVELOPERS subplan will be allocated 100 percent CPU if there are no resources allocated to the DEPARTMENTS subplan.
- C、 The DEPARTMENT subplan will be allocated 100 percent CPU if there are no resources allocated to the DEVELOPERS subplan.
- D、 The second code will not execute because one resource plan cannot be used by more than one subplan.
正确答案:B
答案解析:有