You are working on the cost budget for one project. Which of the following is true()
- A、This process assigns cost estimates to project activities including risks and contingency plans.
- B、The cost baseline will be used to measure variances and future project performance.
- C、This process assigns cost estimates for expected future period operating costs.
- D、The cost baseline is the expected cost for the project.
正确答案:B