If the organizational spending plan has allocated $100,000 for a project, and the high level budget estimate for that project is $200,000; which of the following is accurate?()
- A、The high level budget estimates are inaccurate
- B、The organizational spending plan is inaccurate
- C、The budget is not aligned with the spending plan of the organization
- D、The detailed bottom up budget will need to be adjusted
正确答案:C