If the organizational spending plan has allocated $100,000 for a project, and the high level budget estimate for that project is $200,000; which of the following is accurate?()

  • A、The high level budget estimates are inaccurate
  • B、The organizational spending plan is inaccurate
  • C、The budget is not aligned with the spending plan of the organization
  • D、The detailed bottom up budget will need to be adjusted
正确答案:C