In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communication. According to Metcalfe’s Law, a project with 10 stakeholders has ( ) potential communication channels.
- A、10
- B、45
- C、50
- D、100
正确答案:B