During a planning meeting, Company.com indicates that they intend to make a relational  Database highly available. The application has a pre-requisite that a kernel extension be loaded from /etc/inittab.  How would this be managed in an HACMP environment?()  

  • A、 It can be started with a crontab entry.
  • B、 It can be created as an Application Server.
  • C、 It can be added to a resource group as a dependency.
  • D、 It cannot be done because HACMP provides no method to order application start/stop scripts.
正确答案:B
答案解析: